Sheet 07 — Delivered works

Projects

3projects shown — before and after, with the measured outcome.

PJ-01Controls2025

Glove dipping line PLC retrofit

Glove manufacturer, Kamunting

Condition found

Obsolete controller, no program backup, HMI dead — line run on manual pushbuttons after every trip.

Delivered

Omron CP2E CPU with NB7W HMI, recipe screens for four glove grades, program listing handed over.

Outcome

Grade changeover cut from 40 min to 12 min; unplanned stops down 60% over six months.

Before
After
PJ-02Panels2025

MCC rebuild during shutdown

Palm kernel mill, Manjung

Condition found

Forty-year-old MCC, unlabelled starters, no as-built drawing, repeated overload nuisance trips.

Delivered

New MCC built at Tasek, VSDs on three conveyors, full labelling and DWG as-builts.

Outcome

Cut over inside a 36-hour shutdown window with zero rework calls.

Before
After
PJ-03Handling2024

Carton conveyor roller replacement

Logistics DC, Ipoh

Condition found

Seized gravity rollers, misaligned frame, cartons jamming at the transfer.

Delivered

96 galvanised Ø50.8 mm rollers, frame re-aligned, two driven drum motors at the transfer.

Outcome

Jams at the transfer effectively eliminated; throughput back to design rate.

Before
After